Our Utah team recently tackled an exciting project for Bellevue HOA, showcasing a wide range of our expertise! 🛠️

🔧 Smaller Repair: We discovered a gas line had been installed straight through the storm drain line! To fix this, we installed a CIPP liner, ensuring the damaged section was restored without invasive digging.

🔧 Larger Repair: A pipe penetrating the storm pipeline needed attention. Our crew:

  1. Cleared the gravel from the landscaped area,

  2. Used hydro excavation to expose the pipeline,

  3. Removed the foreign object,

  4. Replaced the damaged pipe section,

  5. Backfilled and restored the area to its original condition.

This project was a great example of how we combine cutting-edge methods like CIPP pipelining and hydro excavation to get the job done efficiently and effectively. 💪